01/19 Runway overlay project video

Essential resurfacing of BNE's main runway has been completed after nearly six months of night works. The resurfacing, which was conducted between midnight and 5am up to six nights a week, replaced the existing 11 year old asphalt in the touchdown zones at either end of the runway with asphalt produced onsite at a specially constructed mobile batch plant. The new asphalt will provide a high quality runway surface for at least the next 10 years. Video by BAC.

Source: BAC